San Jose's temporary pause stops city land-use approvals for data centers and other large energy-use projects until uniform standards are adopted. It freezes 12 proposals now under city review, including Google and Microsoft projects in Alviso, according to SJtoday's Nov. 20 report. A data center is a facility that houses servers and cooling equipment for cloud services and other computing.
The City Council directed the pause in a 10-0 vote on Nov. 17, 2026, with Pam Foley absent, according to the Bay Tribune's account of the vote. Council plans to consider the new standards on Dec. 8, 2026.
Table of Contents
- Which permits are paused?
- How long will the pause last?
- What would the new standards require?
- Who will decide permits next?
Which permits are paused?
The pause covers land-use approvals for data centers and other large energy-use projects. It affects 12 data-center proposals already under city review. That includes Google and Microsoft projects planned in Alviso in North San Jose.
City leaders acted after learning that Google's Alviso facility at 5079/5087 Disk Drive, described as about 250 MW, could receive administrative approval before the new rules existed. For applicants, the practical effect is delay rather than denial. No covered project can move forward through land-use approval until council acts on the standards.
How long will the pause last?
The halt lasts only until council adopts Large Energy Projects uniform standards. That vote is scheduled for Dec. 8, 2026 as an urgency ordinance that would take effect immediately upon approval, according to Data Center Digest's Nov. 18 report. The Nov.
17 action was a policy-direction pause, not a moratorium ordinance. It tells city staff to hold approvals while the standards are finished. A residents' request for a longer pause to study cumulative health, environmental and financial effects remains unresolved. That leaves open whether council will add further review time after Dec. 8.
📨 Get Free California Guides Alerts
Free · No spam · Unsubscribe anytime
What would the new standards require?
The draft standards set minimum benchmarks for energy and water use, air emissions and noise. They include 100% carbon-neutral electricity, limits on potable-water cooling, and strict backup-generator limits. Draft details also require closed-loop or recycled-water cooling.
Maintenance and testing of top-tier generators would be capped at 25 hours yearly. The draft adds labor and community terms. Projects would need prevailing wages, no NDAs or subsidies, plus community-impact fees.
Who will decide permits next?
On Nov. 18 the Planning Commission voted 9-0 to recommend the standards. It changed permit procedure so the Commission, not the Planning Director, holds the first hearing.
That change matters for public participation. A Commission hearing generally provides a public meeting, testimony and a recorded vote before a project advances. People affected can take these steps:.
- Applicants: confirm with Planning whether your project is one of the 12 frozen proposals.
- Nearby residents and renters: watch the Dec. 8 council agenda for the urgency ordinance and hearing rules.
- Job seekers: ask hiring managers whether construction or operations timelines assume approval after Dec. 8.
- Small businesses near Alviso: plan for continued uncertainty until the standards and fees are final.