California could fall 18 years behind because it builds clean power too slowly, rooftop growth has slumped, and grid hookups take years. The Environmental Working Group projects the state will not reach its 2045 clean-electricity target until 2063 under optimistic growth Environmental Working Group analysis. SB 100 is the state law requiring 100% of retail electricity sales from renewable and zero-carbon resources by 2045, with 60% renewables by 2030, according to California Legislature and Energy Commission analyses Assembly analysis of the requirement. That means every unit of power sold to homes and businesses must come from clean sources.
Table of Contents
- How large is the shortfall?
- Why did rooftop solar stall?
- Why are large projects not filling the gap?
- What does delay mean for residents?
How large is the shortfall?
California has about 88 GW of renewable and zero-carbon capacity today but needs about 240 GW by 2045. That requires about 8 GW of new clean generation every year, a pace never achieved, according to KQED reporting on the Environmental Working Group analysis.
The state generated 62.2% of 2024 electricity from clean and renewable resources, including large hydro and nuclear, according to the California Energy Commission. More than one-third still came from fossil fuels. Independent assessments say the state builds only 1-3 GW per year of utility solar but needs 4-7 GW per year.
Why did rooftop solar stall?
Rooftop solar supplied fast, local growth before the payment change. The California Public Utilities Commission adopted the Net Billing Tariff, called NEM 3.0, on Dec. 15, 2022, effective April 15, 2023.
Average rooftop export pay fell from about $0.30 per kWh to about $0.08 per kWh, about 75%, according to pv magazine USA. After the change, residential demand fell 60-80% and installations halved from Q3 2023 to Q1 2024. Industry groups report over 17,000 solar jobs lost and multiple bankruptcies, according to pv magazine USA, PV Tech, and CALSSA reporting cited by SEIA. If rooftop solar stays depressed, the Environmental Working Group projects the 2045 goal slips to 2069, 24 years late.
📨 Get Free California Guides Alerts
Free · No spam · Unsubscribe anytime
Why are large projects not filling the gap?
Large solar and wind farms face long waits for grid review and construction. Projects in the California queue in 2024 averaged 9.2 years from request to connection, the longest among U.S. grid operators. About 63% of PG&E and 70% of SCE transmission projects were delayed, according to Sen.
Scott Wiener's office and 2025 CPUC data. Permits, land limits, and battery needs add pressure. Meeting SB 100 would mean roughly tripling capacity and quintupling batteries by 2045, according to a Nature Conservancy summary of a CPUC ruling and Stanford research. That scale leaves little room for repeated delay.
What does delay mean for residents?
Delay affects workers, renters, and homeowners in different ways. Solar workers face fewer installs and less steady work.
Renters see less local rooftop growth because roofs depend on owners and building rules. Homeowners face a longer wait before clean supply matches state plans. Readers can track local effects without guessing the outcome:.
- Check your electricity bill for usage trends and time-of-use periods.
- Renters can ask property managers about solar, efficiency, or panel upgrades.
- Job seekers can watch community-college, union, and county workforce programs for solar and storage training.
- Residents can follow city and county meetings when large solar, storage, or transmission work is proposed nearby.